Exploration Timeline

Exploration Timeline

Matale/Kurunegala Project

Kingfisher Prospect

Q4 2014

Ground geophysics VLF/magnetics - underway

Land clearing - completed

Roadworks– in progress

Drill pad preparation – in progress

Drill contract – signed with GSMB for 3,000m

Drill hole plan – being designed by SRK

Q1 2015

GSMB 3,000m drilling program

SRK drill program oversight

 

RS Mines (Pvt) Limited

The Queens Mine

Q4 2014

Ground geophysics VLF/magnetics - underway

Land clearing and access - completed

Roadworks – completed

Drill pad preparation – in progress

Water supply and mud pits – in progress

Drill contract – signed with Indodrill for 3,000m

Drill hole plan – completed by SRK subject to ground geophysics optimisation

Metallurgy – samples sent to Bureau Veritas

Q1 2015

Indodrill 3,000m minimum drill program

SRK drill program oversight

 

Paragoda Projects
North & South
Q1 2015
GSMB technical services geological mapping
Land access agreements

 

Southern Projects
Baduraliya, Neluwa&Ambalangoda
CY 2015    
VTEM program over southern projects – quote received

 

Other Projects
St Arnaud Gold Project
CY 2015
Seeking divestment opportunities